PUBLIC UTILITIES - OHIO

In re Complaint of Allied Erecting & Dismantling Company, Inc. v. Ohio Edison Company

Supreme Court of Ohio - July 8, 2021 - N.E.3d - 2021 WL 2828917 - 2021-Ohio-2300

After electric company discovered it had failed to read one of the six electric meters at corporation’s facility for three years, and sent corporation a bill for the three year period, corporation filed a complaint.

The Public Utilities Commission ordered corporation to pay the back bill. Corporation appealed.

The Supreme Court held that:



Copyright © 2024 Bond Case Briefs | bondcasebriefs.com