CONTRACTS - ILLINOIS

PML Development LLC v. Village of Hawthorn Woods

Supreme Court of Illinois - June 15, 2023 - N.E.3d - 2023 IL 128770 - 2023 WL 4003826

Developer brought action against village alleging breach of development agreement under which developer was authorized to fill and grade property in exchange for donating it to village, and village counterclaimed for breach of contract.

After a bench trial, the Circuit Court entered judgment for developer. Village appealed and developer cross-appealed. The Appellate Court affirmed in part, reversed in part, and vacated in part. Developer petitioned for leave to appeal, which was granted.

In a case of first impression, the Supreme Court held that: